Businesses seeking to purchase electricity directly from independent power producers could pay up to KSh1.55 for every unit transported through Kenya's national electricity network under new proposals by the Energy and Petroleum Regulatory Authority (EPRA).EPRA Proposes New Electricity Wheeling Tariffs of Up to KSh1.55

Sign up to Flash News

Your info will be used in accordance with our Privacy Policy

 

The proposed charges are contained in a wheeling framework and tariff methodology published by the regulator as Kenya prepares to open its electricity market to competition, allowing eligible businesses to obtain power from suppliers other than Kenya Power.

Under the proposal, companies using the distribution network would pay KSh0.95 per kilowatt-hour (kWh), while those accessing the transmission network would pay KSh0.60 per unit.

Businesses whose electricity transactions require both networks would face a combined charge of KSh1.55 per kWh.

The proposals are subject to public consultation before EPRA makes a final determination. The regulator has scheduled stakeholder engagement forums between December 7 and 11, 2026, as it seeks views from electricity producers, businesses and other interested parties.

Breakdown of EPRA's Proposed Electricity Wheeling Charges

The proposed wheeling tariffs are intended to compensate companies responsible for maintaining and operating the infrastructure used to transport electricity from generating stations to consumers.

 

Kenya has two major categories of electricity network infrastructure involved in the arrangement: transmission and distribution.

Transmission involves moving electricity over long distances from generating stations through high-voltage power lines, while distribution delivers electricity from substations to businesses and other end users.

Under the proposed methodology, the distribution network charge would stand at KSh0.95 per kWh.

The transmission network charge would be KSh0.60 per kWh.

A business using both systems would therefore pay KSh1.55 for every unit transported through the two networks.

The applicable amount would depend on the infrastructure required to deliver electricity from the producer to the buyer.

The charges would be separate from the actual price agreed between the electricity generator and the business purchasing the power.

This means a company would negotiate the cost of electricity with its chosen producer and separately meet the applicable network charges.

How the New Electricity Charges Would Affect Businesses

The proposed framework would allow eligible companies to purchase electricity directly from independent power producers without constructing private transmission and distribution infrastructure.

Instead, they would pay to use existing electricity networks operated by Kenya Electricity Transmission Company (KETRACO) and Kenya Power.

For example, a business transporting 1,000 units of electricity through both networks would incur KSh1,550 in wheeling charges.

This calculation covers the proposed network charges alone and excludes the cost of purchasing the electricity itself.

Additional statutory levies would also apply.

These include the Rural Electrification Programme levy equivalent to 5 per cent of the value of electricity transported through the network and an EPRA levy of KSh0.08 per kWh.

For 1,000 units, the EPRA levy would amount to KSh80, bringing the combined network charge and EPRA levy to KSh1,630 before the Rural Electrification Programme levy and other applicable costs.

The framework further provides that the network service provider responsible for collecting the charges will remit the applicable levies to their respective agencies.

This arrangement is intended to ensure that electricity producers and buyers can access existing infrastructure while contributing towards its operation and maintenance.

The proposal is particularly relevant to manufacturers, factories and other large electricity consumers whose operations depend heavily on reliable power supply.

How Kenya Power and KETRACO Will Share Wheeling Revenue

EPRA's proposed methodology also outlines how revenue collected from wheeling charges would be distributed between the companies operating the electricity infrastructure.

For transactions involving transmission infrastructure only, KETRACO would receive 91 per cent of the wheeling revenue, while Kenya Power would receive the remaining 9 per cent.

Where electricity transactions use both transmission and distribution networks, Kenya Power would receive 57 per cent, with KETRACO allocated 43 per cent.

The proposed allocation reflects the respective infrastructure assets used to transport electricity to the final customer.

Both companies would therefore earn revenue from providing network services even when the electricity being transported is purchased from an independent producer rather than Kenya Power.

The arrangement is significant because Kenya's electricity market reforms are intended to introduce competition in power supply while retaining the existing national grid as the main transportation infrastructure.

EPRA Proposes 90 Per Cent Network Availability Guarantee

Another important provision in the proposed wheeling framework concerns the reliability of electricity infrastructure.

EPRA has proposed a minimum 90 per cent guaranteed network availability under firm wheeling contracts.

This means network operators would be expected to maintain the agreed level of availability for customers using firm wheeling arrangements.

Where actual availability falls below the guaranteed threshold, payments would be adjusted in accordance with the proposed framework.

The provision is intended to protect businesses purchasing electricity directly from generators against situations where they pay network charges but cannot access the agreed infrastructure availability.

For manufacturers and other industrial consumers, reliability is particularly important because interruptions can affect production schedules, machinery and business operations.

However, the 90 per cent provision relates to network availability under firm contracts and should not be interpreted as a guarantee that electricity supply will never be interrupted.

Who Qualifies to Buy Electricity Directly From Independent Producers?

Although the proposed wheeling charges have attracted attention, the emerging electricity market is not immediately open to every household or small business.

The Energy (Electricity Market, Bulk Supply and Open Access) Regulations, 2026, which commenced on May 8, establish eligibility requirements for consumers seeking direct electricity purchases and access to the national network.

Under Regulation 24, an eligible consumer purchasing electricity in bulk for its own use must meet a minimum load requirement of:

  • Distribution network: At least 1 megavolt-ampere (MVA).

  • Transmission network: At least 10 megavolt-amperes (MVA).

The regulations also require approval of the bulk supply contract by EPRA.

Consumers seeking open access must submit applications to the relevant network service provider, which undertakes a technical assessment before determining whether access can be granted.

The process also involves the preparation and approval of a wheeling agreement.

This means ordinary domestic electricity customers should not expect to immediately choose independent power producers under the new arrangement.

The initial opportunities are directed towards eligible large electricity consumers and licensed market participants.

The regulatory changes are part of Kenya's wider effort to establish a competitive electricity market and encourage investment in power generation and supply.

Businesses can read more about the country's changing energy sector in this report on Kenya's electricity supply challenges.

EPRA Opens Public Participation on New Wheeling Tariffs

The proposed methodology is not yet a final approved tariff schedule.

EPRA is seeking public input before determining the charges that will govern the use of electricity transmission and distribution infrastructure under the open-access framework.

The regulator has scheduled public consultation forums from December 7 to 11, 2026, while receiving written submissions from members of the public and other stakeholders.

 

The engagement is expected to give electricity producers, large consumers, network operators and industry representatives an opportunity to present their views on the proposed methodology.

Stakeholders can also examine how the charges could affect the competitiveness of electricity suppliers and the cost of accessing the national grid.

EPRA's electricity tariff guidelines explain the regulator's responsibility in reviewing and determining electricity pricing structures.

The authority's consultation process will therefore be an important step towards establishing the final charges.

Businesses and industry associations are expected to pay particular attention to the proposed rates, revenue-sharing arrangements and network availability requirements.

The development follows earlier discussions about electricity pricing, including EPRA's previous public review of electricity tariffs.

It also comes amid continuing debate over the cost of power for manufacturers and other commercial consumers, who have repeatedly raised concerns about electricity expenses.

In June, the government announced a reduction of KSh0.2685 per unit in electricity costs, as explained in this electricity price adjustment report.

Meanwhile, Kenya Power has been pursuing other changes to its customer services, including a proposed electricity token advance arrangement.

What Happens Next?

The next major step will be the conclusion of public consultations and EPRA's consideration of submissions from electricity sector stakeholders.

The final methodology will determine the charges applicable to companies using Kenya's transmission and distribution infrastructure to purchase electricity from alternative suppliers.

For eligible businesses, the reforms could introduce greater flexibility in choosing electricity suppliers and negotiating power purchase agreements.

However, the overall cost advantage will depend on the price offered by independent producers, applicable network charges, statutory levies and the technical requirements of accessing the grid.

The proposed KSh1.55 combined wheeling charge is therefore an important component of Kenya's electricity market reforms, but it does not represent the final price businesses will pay for electricity.

EPRA's eventual decision will determine how the new open-access system operates and what eligible consumers pay to transport independently purchased electricity through the national grid.